Rieth-Riley Construction will be milling, adjusting castings, and paving Lincoln Avenue between the Elkhart River bridge and Greene Road and Greene Road from Wilden Avenue to Berkey Avenue. Indiana Avenue’s castings will also be adjusted. The schedule for the crews’ work may change due to weather.
Work begins tomorrow Tuesday, June 19. This is what the scheduled work will be like:
Tuesday, June 19-Wednesday, June 20: Milling Lincoln Avenue from the Elkhart River bridge to Indiana Avenue. There will be flaggers to help direct traffic.
Thursday June, 21: Milling Lincoln Avenue from Indiana Avenue to Greene Road- this will be a one-day closure. The detour route will be Greene Road to Clinton Street to Indiana Avenue to Lincoln Avenue.
Friday, June 22: Milling Greene Road from Elkhart Road (US 33) to Clinton Street and Elkhart Road to Wilden Avenue. Greene Road will be closed in this section. The detour route will be Elkhart Road to Riverside Boulevard to Clinton Street to Greene Road. On Friday, the crews will also be paving Lincoln Avenue from Indiana Avenue to the Rock Run Creek Bridge inside lanes. A flagger will be onsite to direct traffic.
Saturday, June 23: Milling Greene Road from Clinton Street to Berkey Avenue. Greene Road will be closed in this section. The detour will be Clinton Street to Indiana Avenue to Berkey Avenue to Greene Road. Lincoln Avenue will be paved from Elkhart River Bridge to Indiana Avenue on the outside lanes. A flagger will be onsite.
Monday, June 25: Paving Lincoln Avenue from Indiana Avenue to Greene Road. Lincoln Avenue will be closed. The detour will be Indiana Avenue to Clinton Street to Greene Road
Tuesday, June 26: Paving Greene Road from Elkhart Road (US 33) to Wilden Avenue and Elkhart Road to Clinton Street. The detour will be Elkhart Road to Riverside Boulevard to Clinton Street
Wednesday, June 27: Paving Greene Road from Clinton Street to Berkey Avenue. The road will be closed. The detour will be Clinton Street to Indiana Avenue to Berkey Avenue to Greene Road. Castings will be Adjusted on Indiana Avenue
Thursday, June 28-Saturday, June 30: Striping will take place on Lincoln Avenue and Greene Road. There may be lane restrictions while the work is being completed. Castings on Lincoln Avenue and Greene Road will be adjusted while paving.
Follow the City of Goshen, Indiana on Facebook or the City website at goshenindiana.org for the latest updates.