MILLING AND PAVING SCHEDULE

*Please keep in mind that some changes may be made to the schedule due to weather or other unforeseen circumstances.

5th Street milling will be finished today, and will be open after milling is complete until paving.

Tomorrow (May 17), Olive Street will be paved.

The contractors will then pave 8th Street from Lincoln to Madison starting next week.

After 8th street is completed the contractor will then pave 5th Street from the Library to the New US 33 bypass.

Reliance Road was milled from US 33 to Peddlers Village Road, and it remains open at this time. The rest of Reliance Road needs to be milled, but that is in the works of being rescheduled.