The micro-surface and slurry seal contractor, Pavement Solutions, will be mobilizing into Goshen this weekend, pending weather conditions. The following is their anticipated schedule for next week:
- Monday, July 11 and Tuesday, July 12 – Work on 12th and 13th Streets from College Avenue to Plymouth Avenue.
- Wednesday, July 13 and Thursday, July 14 – Work on streets within The Gardens Subdivision. Parking for residents will be provided on Clinton Street in the bike lanes while the streets in the subdivision are closed.
- Friday, July 15 and Saturday, July 16 – Work on streets within the Greenway Subdivision.
In addition, Goshen Street Department is planning to pave per the following schedule:
- Monday, July 11 and Tuesday, July 12 – Dierdorff Road from Kercher Road to Eisenhower Drive North
- Wednesday, July 13 – Friday, July 15 – Chicago Avenue from Pike Street to Indiana Avenue
Please plan accordingly!