NIPSCO Gas Work to Impact S. Indiana Avenue

For more information on this project and other road construction projects visit the City’s interactive Road Closure Map: bit.ly/GoshenRoadClosureMap.

NIPSCO Gas informed the City of Goshen of upcoming road work to install a new gas line that will be taking place on Berkey Avenue and S. Indiana Avenue starting next week on September 5 and going until October 27 (weather dependent). There are three phases to NIPSCO’s work and they are as follows:

Phase 1 – Lane Restrictions (only during the day) with Flaggers from September 5 – September 22 on Berkey Avenue (from Wheatland Drive to S. Indiana Avenue) and S. Indiana Avenue.

Phase 2 – Lane Restrictions (only during the day) with Flaggers from September 22 – October 6 on S. Indiana Avenue north and south of the intersection with Berkey Avenue.

Phase 3 – Lane Shift with 2-Way Traffice from October 6 – October 27 on S. Indiana Avenue at the intersection with W. Plymouth Avenue to just north of the entrance to the parking lot of First Baptist Church.