Select a Section

News & Updates All »

ROAD CLOSURE: 5TH STREET

Tuesday, May 21, 2019

Fifth Street is closed between Madison and Monroe while the city repairs a sinkhole. The road will be closed until Wednesday, May 22, unless work is delayed by the weather. more

MEMORIAL DAY

Monday, May 20, 2019

All City of Goshen offices will be closed Monday, May 27, 2019, due to the Memorial Day holiday. Garbage pickup will be delayed by one day the week of May 27. Trash will be collected starting on Tuesday, May 28. Due to the holiday, the Goshen Board of Works Meeting has been rescheduled to... more

MAY BRUSH COLLECTION

Monday, May 20, 2019

The May brush pickup will begin on Tuesday, May 28. During scheduled brush collections, the Street Department will make only one pass through the city to pick up brush. Please have your brush by the front curb, but not in the street, by that first day in the morning at 7 a.m.  Brush will not... more

Upcoming Events All »

MEMORIAL DAY

Monday, May 27, 2019

All City offices closed.

Shade Tree Board meeting

Monday, May 27, 2019, 7:00pm

Board of Zoning Appeals Meeting

Tuesday, May 28, 2019

9th Street Corridor

The project will consist of constructing a bike and pedestrian trail, from College Ave to Purl St. When completed, we will notice improved pedestrian and vehicle traffic flow through the existing corridor.

The project is slated to begin construction on or about April 9, 2019, with an estimated completion date of late summer 2019. Scroll down for schedule.

Click here for drawings of what the planned road will look like. 

If you have any questions or concerns throughout the duration of the project, please feel free to contact: Goshen Engineering Dept: Leslie Biek, PE, at 574-534-2201 or Abonmarche Consultants: JD McPhail, Project Eng/Supervisor at 574-850-0195.

 

9th St Multi-Use Path

Construction Schedule

4/9/19- 6/19/19

 

 

9th between Jackson and College

Work will be on west side of the road (4/9/19-5/8/19)

Traffic will be northbound only

 

Work will be on east side of the road to install path (5/9/19-6/19/19)

Traffic with be southbound only

6/20/19-7/30/19

 

 

9th between Purl and Jackson

Work will be on west side of road to install path

Traffic will be northbound only

8/1/19 – 8/30/19

 

 

9th and Jackson

Work will be at 9th and Jackson to install table-top intersection for path cross over

The intersection will be closed to traffic

 