The following is a press release from the South Bend-Elkhart Regional Partnership: The South Bend - Elkhart Regional Partnership, in collaboration with numerous community organizations, is launching a Brand Development Project for the region. The goal of this project is to develop a brand and marketing... more

INTERSECTION CLOSURE: JACKSON AND 9TH STREETS

Thursday, September 19, 2019

The City will close the intersection of Jackson and 9th Street beginning Friday, Sept. 20 around noon, to install a table top intersection. This is where the trail crosses from one side to the other and the table top intersection will make this crossing more visible to the traveling public. The... more

Upcoming Events All »

Shade Tree Board meeting

Monday, September 23, 2019, 7:00pm

Board of Zoning Appeals Meeting

Tuesday, September 24, 2019, 4:00pm

Board of Public Works & Safety & Stormwater

Monday, September 30, 2019, 2:00pm

1st Street

Walsh and Kelly, the contractor hired by the City for this project, started working on Phase Two of the First Street Reconstruction Project the week of July 8, 2019. 

The road closure for the second phase of construction is on First Street from Oakridge Avenue to Wilden Avenue. This segment of the road is expected to be reopened to traffic by September 9, 2019. 

Phase One was completed in the summer, in which First Street was reconstructed from Rock Run Creek to Oakridge Avenue.